Why One Full-Service Contractor Can Handle Roofing and Kitchen Remodels
Yes, a full-service contractor can handle roofing and kitchen remodels on the same project. The two scopes rarely overlap in the same square footage, and a single company keeps one schedule, one budget, and one point of contact instead of two.
That matters more than most homeowners expect. When you hire separate crews, you own the coordination. When you hire one, the contractor does.
At MAK Roofing & Construction, we have run combined roof and kitchen projects across El Paso, TX for over 16 years. The pattern is consistent: one plan beats two plans every time.

What Full-Service Actually Means for Your Project
Full-service means one licensed company carries the whole job: permits, materials, labor, inspections, and cleanup. You sign one contract and write one set of checks.
For a combined project, that covers:
- Tear-off and roof decking
- Underlayment and shingles or flat-roof membrane
- Kitchen demolition and haul-away
- Cabinetry, counters, and fixtures
- Final walkthrough and punch list
The alternative is hiring a roofer, then a kitchen remodeler, then hoping their timelines agree. They usually don’t.
When You Still Need a Specialty Subcontractor
Some work calls for a licensed trade the general contractor brings in rather than employs. Electrical, plumbing, and gas line work are the common ones in Texas.
That is not a problem. A full-service contractor manages those subs and stays accountable for their work. You still make one phone call when something goes wrong.
Ask who pulls the permits before you sign anything. On a combined roof and kitchen job, the permit set is the clearest sign of whether one company is truly running the project or just subcontracting it out.
Should You Schedule a Roof Replacement Before a Kitchen Remodel?
Schedule the roof replacement before the kitchen remodel in almost every case. Roof work is loud, dusty, and involves crews walking the perimeter. Kitchen work is precise and expensive. You do not want debris falling near new cabinets.
Why the Roof Comes First
A roof replacement before a kitchen remodel protects the interior you are about to rebuild. If the roof fails mid-remodel, water damage lands on brand-new drywall and flooring.
Three practical reasons to sequence it this way:
- Tear-off shakes the whole structure and can crack fresh tile or grout
- Roofers need driveway and yard access that cabinet deliveries also need
- A new roof can be inspected and closed out before interior work starts
The Texas Department of Insurance windstorm resources explain how roof condition affects insurability in high-wind zones, which is worth checking before you commit to a remodel schedule.
Questions to Ask a Remodeling Contractor Before You Sign
Ask for proof of licensing, insurance, a written scope, a payment schedule, and references from combined projects. Vague answers on any of those are a reason to keep looking.
Run through this list before you sign:
- Are you licensed and insured, and can I see the certificates?
- Who pulls the permits, and who pays for re-inspection if something fails?
- What is the written scope, and what is explicitly excluded?
- How is payment scheduled, and how much is due upfront?
- Can I speak with two past clients who did a roof and an interior remodel together?
- What happens if the schedule slips, and who tells me?
The U.S. Federal Trade Commission guidance on home improvement scams flags large upfront payments and high-pressure signing as warning signs. A contractor who resists a written scope is telling you something.
Never pay for the full job upfront. A large deposit with no written milestone schedule is the single most common way homeowners lose money on remodeling projects.
The Roof Replacement and Kitchen Remodel Timeline
A combined roof replacement and kitchen remodel timeline typically runs several weeks from tear-off to final walkthrough, with the roof phase first and the kitchen phase following. Exact timing depends on roof size, material lead times, and how much kitchen work is structural.
A realistic sequence looks like this:
| Phase | What Happens | Typical Duration |
|---|---|---|
| Roof tear-off | Remove old roofing, inspect decking | 1-2 days |
| Roof install | Underlayment, shingles or membrane | 2-4 days |
| Inspection | City inspection and closeout | 1-3 days |
| Kitchen demo | Remove cabinets, counters, flooring | 2-3 days |
| Rough-in | Electrical, plumbing, gas | 3-5 days |
| Finishes | Cabinets, counters, tile, paint | 2-3 weeks |
| Punch list | Final fixes and walkthrough | 2-5 days |
What Adds Time to the Schedule
Material lead times are the biggest wildcard. Custom cabinetry and specialty countertops can take weeks to arrive, and that wait does not care about your roof schedule.
Other common delays:
- Hidden water damage found during tear-off
- Permit revisions or failed inspections
- Weather that stops roof work mid-phase
- Change orders added after the scope is signed
Build a buffer into your plan. A schedule with no slack is a schedule that slips.
Your Kitchen Remodel Contractor Checklist
Use this kitchen remodel contractor checklist to vet any company before you sign. It works for a kitchen-only job and for a combined roof and kitchen project.
- License number verified with the state
- General liability and workers’ comp certificates on file
- Written scope with inclusions and exclusions
- Payment schedule tied to milestones, not dates
- Permit responsibility stated in writing
- Two or more references from similar combined projects
- Warranty terms in writing for both roof and interior work
- Change-order process explained before work starts
- Cleanup and haul-away included in the scope
- Financing terms confirmed in writing if you are using it
Homeowners searching for a contractor near me often skip the last two items. Both matter. Cleanup disputes and unclear financing terms cause more friction than the work itself.
MAK Roofing & Construction offers bank financing options, so you can confirm terms in writing before the first crew shows up.
A combined roof and kitchen project is manageable when one contractor owns the whole plan. The hard part is finding a company that shows up, finishes on time, and stands behind both scopes.
MAK Roofing & Construction has handled residential and commercial projects across El Paso for over 16 years. We manage the full job from tear-off to final walkthrough, use materials built for the region’s heat and dust, and offer bank financing so the budget does not stall the work.
Get started with MAK Roofing & Construction and turn two projects into one clean, well-managed job.
Frequently Asked Questions
Can one contractor handle both roofing and kitchen remodeling?
Yes, a full-service contractor with in-house roofing and remodeling crews can manage both. The key is verifying the company holds the right licenses and insurance for each trade. Ask whether roofing crews are employees or subcontractors, and confirm the company has completed both project types recently. A contractor with 16 years of combined experience, like MAK Roofing & Construction, typically has the staff and project management systems to run both without delays.
Is it better to replace the roof before remodeling a kitchen?
Replace the roof first in almost every case. A new roof stops leaks and debris from damaging fresh cabinets, countertops, and flooring. It also lets you add attic insulation and ventilation before interior work begins, which improves energy efficiency. If the roof replacement happens after the kitchen, you risk dust, vibration, and water damage undoing your remodel investment.
How long does a roof replacement and kitchen remodel take?
A typical roof replacement takes one to three days for an average home, while a full kitchen remodel runs four to eight weeks depending on scope, permits, and material lead times. When one contractor handles both, the roof is usually completed first, then the kitchen begins. Total timelines range from six to twelve weeks. Weather, inspection schedules, and custom cabinet orders are the most common causes of delays.
What should a roofing and kitchen remodeling contract include?
The contract should list a detailed scope of work for both projects, material specifications, a payment schedule tied to milestones, the project timeline, permit responsibilities, and warranty terms. It must also include the contractor’s license number and proof of general liability and workers’ compensation insurance. Ask for a written change-order process so any additions are priced and approved before work continues.